Contractor using Equalizer FA9TE Hydraulic Flange Alignment Tool on site in Texas

A contractor working on a chemical plant in Freeport, Texas, contacted Equalizer Americas for a solution to the problems they were facing with a misaligned flange.

Maintenance work was scheduled on 18" 600# pipework where the flanges were to be spread and a 2¾” wide blind was to be set in order to test the line. When the contractor began to de-torque and remove the bolts the day before maintenance was scheduled, the flange quickly began to misalign and the remaining bolts bound and seized in the boltholes.

To read more about this Case Study please click here or view in our Technical Library.